38. Commitments  
  Capital expenditure approved:  
  Contracted for 502 517     739 175  
  Not contracted for 440 553     456 801  
943 070     1 195 976  
 

Capital expenditure amounting to R862 million (2019: R1 120 million) is in respect of property, plant and equipment and the remaining balance is in respect of computer software. It is anticipated that capital expenditure will be financed out of existing cash resources.

Bidvest Freight's completion of the LPG tank farm in the port of Richards Bay has been delayed as a result of travel restrictions arising from the COVID-19 lockdown and a new commissioning date is expected in September 2020. At 30 June 2020 R923 million has been spent with an additional R73 million committed to complete and commission the facility. Bidvest Freight has committed R201 million to a LPG tank farm project in Isando, Gauteng. The estimated completion date for the Isando LPG project is March 2022.